Contractor asks Makinde to revisit Ibadan Circular Road project

The contracting firm handling the first phase of Ibadan Circular Road project, ENL Consortium Limited, yesterday, called on Oyo State Governor, Seyi Makinde, to revisit issues surrounding the project, with a view to serving justice on the development.

The Chairman, ENL Consortium Limited, Prince Adewuyi Haastrup, made the call while briefing journalists in Ibadan, on issues surrounding the

delay in the road project, since Makinde assumed office in 2019.

Haastrup, a former deputy governor, said the Makinde-led government risked payment of N10. 6b liability, if the project was not revisited.

He said the contract, which was a private-public partnership (PPP) model, was signed by the late Abiola Ajimobi’s administration in 2017, adding that they immediately commenced work on virgin land with equipment worth billions of naira.

He said: “There has been back and forth on the project, following the ousting of the All Progressives Congress (APC) from the Agodi Government House in 2019.

“Makinde had announced the termination of the contract over an alleged delay in delivering the project. The contract was for a 32-kilometre road, starting near the First Technical University on Lagos-Ibadan Expressway and terminating at Badeku Village, along Ife-Ibadan Road.”

Haastrup said the governor refused to grant their request, which included writing a Letter of Assurance of Continuity to continue the job, adding: “He promised he would write us Letter of Assurance of continuity for the work. He later did not honour his words. His strategy was that when we are out of the fund, nobody would tell us to leave. But to his dismay, we deployed brand new equipment worth N5m to the site. We are working.”

He said the delay had to do with a lack of fund to pay the Italian company, which did the design and others, including clearing the site, the earthwork and paying compensation to the villagers.

It would be recalled that the state government had complained that the project was slow. But, Hasstrup said that was not enough a reason to treat them in that manner.

He said all they asked for was a Letter of Assurance to continue with the job, adding that ENL Consortium had told the governor of the agreement’s implication, which would have them pay 10 percent penalty of N6.7b, and everything totalling N10.6b.